Published Date:2026-11-18
Views:3 Output per hour comes from four numbers: bucket capacity, fill factor, cycles per hour and job efficiency. On a 2.2 t JYH25 with a 0.08 m³ bucket, an 18-second cycle and 0.80 efficiency, that is 11.5 m³ of loose spoil an hour — roughly 23 m of 0.4 m trench. Every figure below is built from that one line.
Excavator output is a multiplication, not a specification. Only one of the four inputs appears on a brochure; the other three belong to your site, your soil and your operator. That is why two contractors can run identical machines on the same street and report production figures that differ by half.
The four inputs, in the order you should collect them:
Put them together and the arithmetic is short: capacity × fill factor × cycles per hour × efficiency. Take the JYH25 mini excavator, the 2,200 kg machine we build at Jinyuhang around a 15.2 kW Yanmar 3TNV80 with a 2,410 mm dig depth. A 0.08 m³ bucket at 0.90 fill carries 0.072 m³ per pass. At 18 seconds a cycle the machine completes 200 cycles in an hour, which multiplies out to 14.4 m³ of loose material at the theoretical ceiling. Apply 0.80 efficiency and the honest figure is 11.5 m³ an hour.
Two conversions finish the job. Divide by a swell factor of 1.25 for ordinary soil and you get 9.2 m³ of bank volume per hour. Divide that by the 0.4 m³ in each metre of a 400 mm wide, 1,000 mm deep trench and the machine lays about 23 m of trench an hour, spoil pile permitting.
Run the same arithmetic on the 900 kg JYH12 mini excavator and the number drops further than most buyers expect. A 0.04 m³ bucket, a 22-second cycle and 0.83 efficiency give 4.9 m³ an hour. Less than half the weight, and less than half the output.
The table below pairs the published specifications of each JYH model with the bucket class that machines of that weight normally carry, then runs the formula at ordinary-soil values: 0.90 fill, 20-second cycle, 0.80 efficiency. Bucket capacity is the one column we do not publish as a fixed spec, because the bucket you order decides it — treat those figures as class typicals and check the stamp on your own bucket before you plan a job around it.
| Model | Operating weight | Max dig depth | Breakout force | Typical bucket (heaped) | Output, ordinary soil |
|---|---|---|---|---|---|
| JYH06 | 660 kg | 1,091 mm | 3.5 kN | 0.020–0.030 m³ | 1.5–2.5 m³/h |
| JYH12 | 900 kg | 1,717 mm | 7.2 kN | 0.030–0.040 m³ | 3–5 m³/h |
| JYH15 | 1,275 kg | 1,991 mm | 9 kN | 0.040–0.055 m³ | 4.5–7 m³/h |
| JYH17-A | 1,525 kg | 2,340 mm | 13.5 kN | 0.050–0.060 m³ | 6–9 m³/h |
| JYH25 | 2,200 kg | 2,410 mm | 20 kN | 0.070–0.080 m³ | 9–13 m³/h |
| JYH27 | 2,540 kg | 2,590 mm | 20 kN | 0.080–0.090 m³ | 10–15 m³/h |
Read the columns together rather than the output column alone. The 660 kg JYH06 reaches 1,091 mm and clears a 690 mm gate; it moves 1.5–2.5 m³ an hour, which is ample for planting beds and hopeless for a 300 m³ footing excavation that a 2.5 t machine finishes in four days. Narrow access and high output are still a trade you cannot make with one machine.
There is a second reason the small end of the table looks weak. Cycle time does not shrink in proportion to machine size. A 660 kg micro still needs 20–24 seconds to dig, swing and dump, mostly because its swing motor and hydraulic flow are sized for a 3.5 kN breakout force rather than production digging. You pay for the access, not for the cubic metres.
Soil and cycle time, in that order. The same 0.08 m³ bucket on the same JYH25 produces three very different days depending on what is in the ground and how far the operator has to swing.
| Input | Loose sand, short swing | Ordinary soil, 90° swing | Stiff clay or broken rock |
|---|---|---|---|
| Fill factor | 0.95 | 0.90 | 0.65 |
| Cycle time | 16 s | 18 s | 28 s |
| Job efficiency | 0.90 | 0.80 | 0.65 |
| Output from a 0.08 m³ bucket | 15.4 m³/h | 11.5 m³/h | 4.3 m³/h |
Nothing in that table changed except the ground and the operator’s working conditions, and the answer moved by a factor of 3.6. A buyer who compares a 2.2 t machine with a 2.5 t machine is arguing over roughly 15% of output; the same buyer who moves from a tidy site to a clay-filled backyard loses 60%.
Swing angle deserves its own line because it is the variable contractors most often ignore. Every extra second in the cycle costs production twice: it reduces the number of passes and it lengthens the queue behind the machine. Swing 180° to a stockpile instead of 90° to a waiting truck and a 20-second cycle becomes 26 seconds, cycles fall from 180 to 138 an hour, and the output of that 0.08 m³ bucket drops from 12.9 m³ to 9.9 m³ before efficiency is even applied. On a 400 mm trench that is the difference between 30 m and 23 m of progress in an hour.
Repositioning is the quiet one. On trench work a mini excavator tracks forward every 2–4 m, and on a tight site it may also have to lift the blade, reposition, and re-level before the next bite. Count that honestly and a machine that looks like a 12 m³/h unit in a demo delivers 9 m³/h across a shift, which is exactly what the efficiency factor in the formula is there to absorb.
Spoil is not soil. Material that occupied 1 m³ in the ground occupies 1.25 m³ in the bucket for ordinary soil, 1.35–1.45 m³ for clay, and only 1.10 m³ for sand and gravel. Digging a 40 m³ pit therefore produces 50 m³ of spoil to move, and a contractor who prices the truck by bank volume will be one load short.
The first mistake is quoting loose cubic metres as if they were bank cubic metres. Specification sheets, bucket stamps and site measurements all speak a slightly different language, and the 20–30% gap between them is usually the entire margin on a small earthworks job. Decide before you quote whether you are paid for what left the ground or what arrived at the tip.
The second is the 60-minute hour. Machines do not work 60 minutes; a well-run site gets 48–51. Using 60 inflates output by a fifth, and the error compounds across a week of work.
Third, output figures get repeated without their conditions attached. “This machine does 15 m³ an hour” is meaningless unless it names the bucket, the soil and the swing — and the same machine in clay does 4.3. When we spec a machine at Jinyuhang, we ask for the trench section, the soil and the dump position before we talk about tonnage; those three answers decide the model far more reliably than a horsepower figure.
Fourth, bucket size is treated as free production. It is not. Oversize the bucket on a 1.5 t machine and the 9 kN breakout force of the JYH15 cannot fill it in clay, so cycle time rises while payload stays flat, and the operator spends the day curling a half-empty bucket. The reverse error is just as common: buyers order the smallest bucket to save money and then pay for it in cycle count.
One practical shortcut for anyone planning a trench: measure ten cycles with a stopwatch, divide by ten, and use that number instead of any figure in this article. Site-measured cycle time beats published output every time, and it takes about four minutes.
Between 3 and 5 m³ of loose material an hour in ordinary soil, using a 0.03–0.04 m³ bucket and an 18–22 second cycle. In stiff clay expect closer to 2 m³/h; in sand with a short swing, 6 m³/h is reachable.
Use 18–20 seconds for a 1.5–2.5 t machine swinging 90° to a truck, 22–24 seconds for a machine under 1 t, and add 5–6 seconds for every extra 90° of swing. Measure on site before you commit to a deadline.
No. Output only rises if the machine can fill the bucket in its normal cycle. A bucket that is too large for the breakout force leaves the machine curling half-loads, which lengthens the cycle and cancels the gain.
At 400 mm wide and 1,000 mm deep the trench holds 20 m³ of bank material. At roughly 9 m³ of bank volume an hour, plan on 2.2 hours of digging plus 20–30% for repositioning and spoil handling — about three hours on a clean site.
Both, for different reasons. Bank volume sets what you are paid and how much ground you are removing; loose volume sets how many truck loads leave site. Convert with a swell factor of 1.25 for ordinary soil and 1.40 for clay.
This article is original and edited by our website. Reproduction requires the author’s consent, and please cite the source together with the link to this page.